V&A Construction Update: Excavation Works 90% Complete

Excavation works at the V&A site have been progressing well and are now 90% complete.

The B6 basement level (and lowest level of the building) has almost been fully excavated, with just the eastern side remaining. This is no mean feat, with 130,000 cubic metres of sand moved out of the basement during this phase of construction. V&A is unique in having six basement levels, as most developments only have three or four; this means more parking for residents.

 

Watch the June construction update

 

In the coming weeks, the next steps are to finish the full excavation and commence the sheet piling on the lift cores (the sheet piling has already arrived on site). The west tower core and lift will commence first, followed by the east tower.

Afterwards, construction will begin on the 800mm thick B6 raft slab, which will see 4,800 cubic metres of concrete poured over the next few months.

Pre-planning for the tower crane is also complete, which will be a significant milestone for the V&A build. The first tower crane to due to be put in place and start work in mid-June, with another two tower cranes to be added over the coming months.

Limited residences remain at V&A Broadbeach

To secure a 1, 2, 3 or 4 bedroom apartment, or one of the spectacular penthouses, enquire with our sales team today.

04 Jun 2025

SHARE:

REGISTER NOW

Enter your details below to be among the first to discover Victoria & Albert.

Please enter a number from 1000 to 9999.

VISIT OUR DISPLAY TO EXPERIENCE STATE-OF-THE-ART
IMMERSIVE WALKTHROUGHS OF THE V&A RESIDENCES

Shop 1/90 Surf Parade, Broadbeach QLD 4218
1800 733 046

Instagram